Žitný ostrov – Gabčíkovo region – waste water diversion and treatment

Client VODOHOSPODÁRSKE STAVBY – ecological company as. Construction period August 2022 – December 2023 Description of objects: The subject of the performance is the construction of sewerage in the villages Baka and Jurová in total length 15,022 km (of which 10,078 km are gravity sewerage and 4,944 km pressure sewerage), including 10 pumping stations and…

WWTP Kolárovo – reconstruction and extension – Ist stage

Client Západoslovenská vodárenská spoločnosť, a.s. Construction period March 2022 – August 2023 Construction technology: The subject of the project is the reconstruction and extension of the existing Kolárovo WWTP to a total capacity of 13,750 PE. The construction of the WWTP will take place during full operation of the original pumping station resp. without limiting…

Motorway D3 Žilina (Brodno) Kysucké Nové Mesto – feeder

Client National Motorway Company a.s. General contractor Metrostav DS a.s. Construction period February 2022 – February 2023 Destription of the objects: Object 543 Modification of water supply DN 800 at km 15,830 – 16,700 D3 Object 543 Cathodic protection of water supply relocation DN 800 at km 15,830 – 16,700 D3 Technology of construction: Relocation…

ŽSR, Completion of the Žilina -Teplička railway shunting station

Investor Railways of the Slovak Republic General contractor EUROVIA CS, a.s. – organizational unit Slovakia Construction period March 2021 – December 2023 Description of the objects: SO 53-37-01 Žilina Strážov – Váh, rain sewerage SO 53-37-02 Žilina Strážov – Váh, relocation of water mains SO 53-37-03 Žilina Strážov – Váh, relocation of sewerage Construction technology: SO…