Highway Tunnel Bôrik

Highway D1 Mengusovce – Jánovce, section km 0.000 to 8.000, part tunnel Bôrik

Client

Národná diaľničná spoločnosť,a.s. Bratislava

Superior Contractor

“IS – Marti Contractors” Consortium

Construction period

April 2006 – December 2009

Objects description:

  • east portal section
  • west portal section
  • right tunnel tube
  • left tunnel tube
  • escape galleries
  • roadway and pavements in tunnel
  • waste waters discharge
  • drainage waters discharge

Construction technology:
Tunnel was driven by NATM – (New Austrian Tunnelling Method) – by using drilling and blasting works.

Executed works:

  • excavation and support of portal cuts
  • driving of the pillar galleries, profile 51,23 m2, length 180 m
  • concreting of pillars
  • excavation of tunnel tubes, the profile 80,2 m2
  • length of LT (left tube) 943,07 m
  • length of RT (right tube) 929,03 m
  • amount of shotcrete 19 000 m3
  • amount of muck 175 730 m3
  • period of driving 18 months 10/2006 – 03/2008 (including driving and concreting of the pillar galleries)
  • excavation of escape galleries, length 64,2 m, profile 30,41 m2
  • secondary lining
  • LT: length of driving part 943,07 m
  • LT: length of cut and cover part 56,53 m
  • RT: length of driving part 929,03 m
  • RT: length of cut and cover part 63,78 m
  • block length: 10 m
  • amount of concrete: 28,300 m3 – driving part
  • amount of concrete: 2 600 m3 – cut and cover part
  • the block length: 10 m
  • concreting period: 11 months (11/2007 – 09/2008)
  • drainage
  • roadway
  • pavements
  • cable routes