Bratislava, Hradská street – Reconstruction of the water supply

Client

Bratislavská vodárenská spoločnost, a.s.

Construction period

May 2022 – September 2022

Description of objects:
The subject of the performance is the realization of the public water supply pipe on Hradská street, that includes to provide the necessary permits and engineering activity necessary for the realization of the construction. The existing water supply pipe will be replaced by the new one with total length of reconstruction 1338.2 m.
Laying of the water supply pipe from TVLT DN 100 in a total length of 179.9 m and the water supply pipe from TVLT DN 150 in a total length of 1158.30 m with 15 pieces of underground hydrants DN80.

Construction technology:

  • Renovation of the DN150 PVC water supply pipe for the new TVLT Natural DN150 pipe marked as branch V1 with length 1,158.3 m with connection of 103 pieces of connections
  • Renovation of a DN100 steel water supply pipe for a new TVLT Natural DN150 pipe marked as branch V2 with length 146.9 m with connection of 5 pieces of connections
  • Connection of secondary existing water supply lines, namely:
    Branch V3 from the TVLT Natural DN100 pipeline, length 7.5 m
    Branch V4 from the TVLT Natural DN100 pipeline, length 17.0 m
    Branch V4 from the TVLT Natural DN100 pipeline, length 8.5 m