Reconstruction of WWTP and sewerage in local parts of the town Litomyšl – Nedošín, Lány

Investor

Town Litomyšl, Czech Republic

Main contractor

JV of companies: PKS stavby a.s, Žďár nad Sázavou and Profistav a.s., Litomyšl

Construction period

October 2013 – December 2014

Description of objects and realized works:

  • BO 01 and BO 06 – Measuring objects – newly built underground reinforced concrete objects on the level of mechanical pre-treatment and underload at the inlet of the WWTP.
  • BO 02,03,04,07: The inlet – plenum chamber – a new reinforced concrete object for influent sewage to a WWTP
  • BO 05 Reconstruction of existing manipulation tanks for rainwater tanks
  • BO 08 Mechanical pre-treatment – sanitation of the original object
  • BO 09 Reconstruction of existing sedimentation tank
  • BO 12 Reconstruction of existing settlement tank.
  • BO 16 Chemical coagulation of phosphorus – reinforced concrete structures for technology.
  • BO 18 Reconstruction of the old dysfunctional settlement tank
  • BO 19 Manipulation pit – the abolition of the existing pit chambers
  • BO 20 Reconstruction of the storage tank
  • BO 21 Pipelines – technological distribution DN 100 – DN 600 realized ​​in open cut
  • SO 22 Demolition and relocation of utilities – necessary transhipment existing utilities in WWTP area.
  • SO 24 Fencing – realization of new fencing

Within each object assembling composite and stainless steel elements.