Client
Severoslovenské vodárne a kanalizácie, a.s. Žilina
Construction period
March 2019 – June 2020
Technology of the construction:
- Extension of the water main in Žilina municipality, Brodno district.
- Water supply will be connected to the existed water supply in location managed by SeVaK, a.s..
- Damaged parts of the existed local water supply will be removed.
Executed works:
- Construction of the water main, pipeline HDPE PE100 PN10 Ø 110/6,6 mm, in the total length of 862 m
- Construction of the 40 pcs of water connections, pipeline HDPE PE100 PN10 Ø 32/2,0 mm, in the total length of 240 m