Žilina – Brodno – Extension of the water main

Client

Severoslovenské vodárne a kanalizácie, a.s. Žilina

Construction period

March 2019 – June 2020

Technology of the construction:

  • Extension of the water main in Žilina municipality, Brodno district.
  • Water supply will be connected to the existed water supply in location managed by SeVaK, a.s..
  • Damaged parts of the existed local water supply will be removed.

Executed works:

  • Construction of the water main, pipeline HDPE  PE100  PN10  Ø 110/6,6 mm, in the total length of 862 m
  • Construction of the 40 pcs of water connections, pipeline HDPE  PE100  PN10  Ø 32/2,0 mm, in the total length of 240 m